Running short-circuit analysis

This guide shows you how to run short-circuit analysis on your single-line diagram and interpret the results.

Before you start

Ensure your diagram has:

  • At least one power source (utility feed or generator)
  • Complete network with all components connected
  • Utility feed short-circuit MVA and X/R ratio specified
  • Generator subtransient reactance (X''d) if applicable
  • Transformer impedance percentages
  • All component voltage ratings

Missing source impedance data causes analysis to fail.

Running the analysis

  1. Open your project in the SLD editor.
  2. Verify all sources have impedance data.
  3. Click Run Short-Circuit button in the toolbar.
  4. EKX runs the validated three-phase maximum-current short-circuit calculation.
  5. Analysis executes in 2-5 seconds.
  6. Results appear on the single-line diagram.

Selecting fault type

Three-phase fault (recommended for equipment rating):

  • Highest fault current
  • Use for breaker interrupting capacity
  • Most conservative

The current production workflow supports three-phase maximum-current analysis only. Phase-to-phase, single-phase, minimum-current, and all-fault-type workflows require separate validation before they are enabled.

Viewing results

Results display shows:

Per bus:

  • Fault current magnitude (kA)
  • Peak fault current (kA)
  • Fault MVA
  • Voltage during fault

Critical buses:

  • Highest fault currents highlighted
  • Identifies locations needing high interrupting capacity

Summary:

  • Maximum, minimum, average fault currents
  • System fault level

Interpreting fault currents

High fault currents (>20 kA at 480V):

  • Near utility connection or large generators
  • Require high interrupting capacity breakers (65kA, 100kA AIC)
  • May need current-limiting fuses
  • Higher arc flash hazard

Medium fault currents (10-20 kA):

  • Middle of distribution system
  • Standard industrial breakers (25kA, 42kA AIC)
  • Typical for most equipment

Low fault currents (<10 kA):

  • End of long feeders
  • Far from sources
  • Lower interrupting capacity acceptable
  • Verify protection sensitivity

Compare fault currents to breaker interrupting capacity ratings. Breaker AIC must exceed fault current at installation point.

Equipment verification

Circuit breakers:

  • Interrupting capacity ≥ fault current
  • Example: 20 kA fault requires ≥22 kA AIC breaker
  • Use next standard size up for safety margin

Buses and switchgear:

  • Short-circuit withstand rating
  • Based on peak current and duration
  • Verify bracing adequate

Cables:

  • Short-circuit withstand: I²t rating
  • Duration typically 0.1-1.0 seconds
  • Larger cables have higher withstand

Coordination verification

Short-circuit results used for protection coordination:

  1. Plot device time-current curves.
  2. Mark fault currents on the plot.
  3. Verify upstream device is slower than downstream at fault current.
  4. Maintain separation for selectivity.

ekx may support coordination plotting in future versions.

Arc flash considerations

Fault currents determine arc flash incident energy:

Higher fault current:

  • Higher incident energy
  • Greater arc flash hazard
  • More extensive PPE required
  • Larger arc flash boundary

Lower fault current:

  • Lower incident energy
  • Reduced hazard
  • Less PPE needed

Arc flash analysis is planned for a future release and will use short-circuit results as input. This feature is not yet available.

Troubleshooting failed analysis

"No sources defined":

  • Add utility feed or generator
  • Verify source has impedance data

"Missing transformer impedance":

  • Set transformer Z% in properties
  • Use typical value if nameplate unavailable

"Network not connected":

  • Check for isolated components
  • Ensure all buses connect to main system

"Calculation did not converge":

  • Verify all impedances are positive, non-zero
  • Check for missing component data
  • Review validation warnings

Exporting results

Export short-circuit data for reporting:

  1. Click Export Results button.
  2. Results save to debug-exports/sc-debug-[timestamp].md.
  3. File contains fault currents for all buses.
  4. Include in project documentation.